How this register works.
The projects register is a record of what Council's published plans list; not a delivery record. This page says exactly what each figure means and what our records do not contain.
Every project uses its Council project number, written AC-2068. Projects with no Council number keep a local ID such as ACH-004 and are marked No Council ID.
What a planned allocation is
A planned allocation is the amount Council's adopted program allocates to a project in a financial year, as published in the delivery program and operational plan schedules. It is what the plan says will be spent or earned that year; nothing more.
- It is not an approved baseline. The earliest observed plan figure for a project is not its original approved lifetime budget; no verified approved baseline exists in our records, so those fields show “Not established” rather than $0.
- It is not actual spending. No project in the register has an established final cost or completion date. Nothing here should be read as money spent or work completed.
- Plans change between adopted programs. Where a same-year allocation differs, we show only that difference, with the caption that its cause and any effect on lifetime project cost have not been established from these sources. We describe the published difference and nothing more.
What a removal means
A project removed from the 2026–30 program is not cancelled and not waste. It may be completed, paused, merged into another project or deferred. For each of the 25 removed listings we quote Council's stated reason where it exists in our records; where it does not, we, we say so instead of guessing.
Removals are shown with their prior four-year planned figures from the 2025 plan, labelled as planned, never as spent. Where a removal says works were incorporated into another project ID (for example Northern Valley), both IDs are linked and the works must not be double-counted.
What is not in our records
- FY2015–FY2023 adopted budgets and actuals are not included. A blank year on a project card is missing evidence, not zero spend.
- No verified original approved baseline, final cost or completion date. Where our records have no documented amount or date, the page shows “Not established”; never $0 and never 0%.
- Progress-report leads that are not yet confirmed by Council are excluded from the cards. Leads from annual report narratives and progress schedules have not been checked row by row against sources; they do not appear on public project pages. A reported percentage is not presented as completion.
- Contract values are not added to project totals. Procurement estimates, where shown at all, are labelled “procurement estimate, not spent” and never counted as expenditure.
- Funds stay separate: General, Water and Wastewater. They are not combined into one spending total.
This is not an audit
The register is built from published Council documents with AI-assisted extraction and human guidance. It has not been independently audited or verified, it is not legal, accounting or professional financial advice, and it is not an official AlburyCity publication.
Who is behind this project, including the initiator's connections to AlburyCity, is set out in full on the About page: read the author disclosure ↗. That wording stands as written there; it is not restated or softened here.
If you find an error, tell us via About & contribute; include the project ID (for example AC-2034), the figure, the financial year and the source document page. Back to the projects register →